HS2 TBMs complete three quarters of Chiltern tunnels

Aerial-view-of-the-Little-Missenden-vent-shaft-under-construction-Summer-2023-300x200.jpg

The two tunnel boring machines (TBMs) delivering the longest tunnels on the High Speed 2 (HS2) railway have passed the three quarters mark.

TBMs Florence and Cecilia have completed over 12km of the 16km Chiltern twin-bore tunnels, passing the fourth of five ventilation and emergency access shafts, 800m from the village…

HS2 reveals designs for final Chiltern Tunnel portal

chiltern-tunnel-north-portal-hs2-300x200.png

High Speed 2 (HS2) and Align JV have revealed the designs for the north portal of the Chiltern Tunnel.

This is the final portal to be designed and the last of seven key structures for HS2’s longest tunnels. The design features two perforated concrete hoods that will cover the track, extending…

Halfway stage achieved by both bores on HS2’s Chiltern Tunnel

Chiltern-tunnel-curving-out-of-sight-November-2022-50596-300x200.jpg

Both tunnel boring machines (TBMs) being used to drive the 16km long tunnels through the Chilterns for High Speed 2 (HS2) have just passed the halfway point on their journeys towards the north portals at South Heath in Buckinghamshire.

The Herrenknecht TBMs – named Florence and Cecilia – were the first…

HS2 | Construction progresses on record-breaking Colne Valley Viaduct

colne-valley-viaduct-snow-3-2-300x200.jpg

HS2 engineers from Align JV (Bouygues, VolkerFitzpatrick, Sir Robert McAlpine) are approaching halfway on the first module of the Colne Valley Viaduct, which has featured the team working through 60 nights to avoid disruption to the local roads.

HS2 Phase 1 will see the construction of more than 500 bridging structures,…

HS2 contractors ‘lose’ bentonite into aquifer

Chalfont-St-Peter-vent-shaft-excavation-July-2021-3-300x200.jpg

High Speed 2 (HS2) contractors have admitted leaking 1,500m3 of bentonite slurry into a chalk aquifer that traditionally carries water eventually supplied to Londoners – as the Environment Agency faces a legal challenge over its approval of the works.

The Align join venture – formed of Bouygues Travaux Publics, Sir Robert…